Must a company be able to reach the new track to upgrade a tile?
The rulebook's upgrade test names any segment on the new tile, and the forum's reading matches it.
- 1830: Railways & Robber Barons rulebook · Rulebook · Upgrading Track Tiles (6.2.2)
- NateStraight · Community · 2021-10-23
- clearclaw · Community · 2014-10-11
- EricHogue · Community · 2016-10-01
- RvdH83 · Community · 2018-01-16
- Excalabur · Community · 2019-09-14
- garrett361 · Community · 2018-01-16disagrees
No. The company needs an unblocked route from one of its stations to at least one track segment on the upgraded tile. That segment may be old track, so the new track need not be reachable and need not connect to the company's existing network.